de Blasio's DDC defiantly shady about East River Park reconstruction

 

AMNY

A much sought-after ghost study of the East Side Coastal Resiliency (ESCR) that mysteriously could not be traced has suddenly been released to the public, but it is almost unreadable due to heavy redactions.

East River Park Action has been pulling at the threads of the East Side Coastal Resiliency (ESCR) project for about three years now.  The organization—consisting of concerned Lower East Side residents—are opposed to this $1.4 billion plan that would reconstruct approximately 57 acres of coastal parkland from East 25th Street to Montgomery Street.

In 2018, the rationale for moving forward with the ESCR project, rather than a less invasive one, was said to be based on a “Value Engineering Study.” The East River Park Action group filed a Freedom of Information Law request but was told in January by the City’s Department of Design and Construction (DDC) that they did not have this report on file.  East River Park Action is a strong opponent of the ESCR project since the reconstruction will remove over 1,000 trees, which will subsequently be replaced after construction, and pack the land with about eight to ten feet of fill to help elevate the park, making it flood-resistant.

Hurricane Sandy devastated the Lower East Side in 2012, and in response community leaders and city planning agencies had several discussions on how to prevent such large-scale coastal flooding in the area. Originally, a far less expensive plan was discussed for several years but was discarded in favor of the ESCR in 2018. The reasoning for this shift was based on a study that would showcase the pros and cons of this project as well as other pertinent information, which was announced by Mayor Bill de Blasio.

However, according to a tweet by Kirsten Theodos, who shared the report over social media the majority of its pages are blacked out, making it unreadable.

“The new City plan will destroy 57 acres of coastal parkland, fell nearly 1000 mature trees and eliminate the only large outdoor greenspace residents on LES for recreation and wellness. The City plan is twice as expensive, provides no interim flood protection during the many years of construction, & requires unprecedented ecological destruction of the largest municipal park on the LES impacting the residents of the predominantly low income, BIPOC neighborhood,” Theodos wrote in a tweet.

As stated on NYC ESCR project’s website, the plan is set to create “boundaries of this project correspond with the natural “pinch-points” in the 100-year floodplain: areas where the land is higher along the coastline, making it easier to close the system off from water entering from the north and south. The project design integrates flood protection into the community fabric, improving waterfront open spaces and access, rather than walling off the neighborhood.”

 The report’s findings—which states that it was prepared for the City of New York Office of Management and Budget”—is entitled “East Side Coastal Resiliency Elevated Park Alternative Feasibility Analysis” and is dated April 24-26, 2018.  The rest becomes a series of blackened lines where certain particulars have been redacted from public view.