(Larry Penner -- transportation
advocate, historian and writer who previously worked for the Federal
Transit Administration Region 2 New York Office. This included the development, review, approval and oversight for billions in capital
projects and programs for NY MTA, NYC Transit, Long Island Rail Road, Metro North Rail Road MTA Bus, NYC DOT Staten Island Ferry. Nassau County NICE Bus, Niagara Frontier Transportation Authority (NFTA) along with 30 other transit agencies in NY & NJ).
It appears that her top five priorities are
(1) $33 billion Gateway Tunnel
The
full build $33 billion Gateway Tunnel project needs up to $16.5 billion
from the Federal Transit Administration, along with $8.25 billion from
NY and the same amount from NJ to support a future FTA New Starts Full
Funding Agreement. While there is funding in place for the $1.8 billion
Portal Bridge, the balance of funding to pay for the
reduced scope $12 billion ($6 billion NY/NJ/ & $6 billion federal)
two new Hudson River tunnels and rehabilitation of existing tunnels remains outstanding.
(2) $6.9 billion Second Avenue Subway Phase 2,
The
2nd Avenue Subway Phase 2 needs $6.9 billion. This project is counting
on a Federal Transit Administration Full Funding grant agreement for
$3.4 billion coming from Washington. The project completed NEPA in
November 2020 with FTA issuing a formal environmental review finding.
Receipt of the FTA FFGA in past years never took place. Time
is still needed for completion of design, engineering, business
relocation, real estate acquisition and private property easement
rights. There is also the need for agreements with NYC and various
owners of underground utilities including water, sewer, gas, electric,
steam and cable before being ready to commence construction by 2023. Successful completion for all of the above may need many one to two years
(3) $8 billion Penn Station Transformation,
Last
year, former NY Governor Cuomo announced a new Penn Station South
Station at a cost of $8 billion. It would consist of 4 new platforms
and 8 tracks with connections to the existing Penn Station and NYC
Transit Subway Stations. A consultant has been hired to conduct a
planning feasibility study. This was a part of his $16 billion NY Empire
Station Complex proposal. NY Governor Hochul has her own $8 billion reduced scope proposal for similar Penn Station improvements .
(4)
New mulit billion dollar Interboro Express Brooklyn to Queens Subway.
Was her ghost speech writer aware that for decades this has been known
as the TriBoro X Express? It includes service connecting the Bronx to
Yankee Stadium. The
Triboro X Subway Express (new subway line connecting the Bronx, Queens
& Brooklyn would require several billion. The MTA initiated another
new planning feasibility study last year. There is no public timetable
for completion of the study.
(5) $10 billion Cross Harbor Freight Tunnel The Port Authority Cross Harbor Freight Tunnel requires $10 billion. This year the project will celebrate
its 31st year anniversary of being stuck in the planning and
environmental review phase. It is anticipated that FHWA may issue a NEPA
finding later this year.
These
first two projects are up to two years away from being shovel ready for
construction, The last three are up to a decade or more away from being
shovel ready for construction.
You can learn a great deal concerning what transportation projects and issues Governor Hochul is not interested in by omission.
Her are the following projects she did not include her support today during her speech.
No
support for the MTA initiation of Congestion Toll Pricing. This is
needed to raise $15 of the $51 billion MTA 2020 - 2024 Five Year Capital
Plan.
No update as to who her five appointees will be to the MTA Traffic Mobility Review Board.
The
new Port Authority 42nd Street Manhattan Bus Terminal needs $10
billion. This project is still in the planning and environmental review
phase. Only $3.5 of the estimated $10 billion cost is actually approved
within the current 2016 - 2026 Port Authority Capital Plan. They are
counting on future federal assistance to make up the shortfall.
The
LIRR estimates that it would cost $18 million per mile to extend
electrification into existing diesel territory. Besides third rail, you
also need a series of electrical sub stations for each branch. This
might also involve land acquisition, business and utility relocation
costs. There is also the costs for new high level platforms and
additional parking at stations.
The $3.6
billion LIRR electrification of Port Jefferson branch from Huntington
to Port Jefferson originally discussed in the 1980's is still in the
planning phase.
The $2.2
billion Light Rail between Jamaica and Long Island City on the old
Lower Montauk LIRR branch in Queens, has yet to advance beyond a final
planning study which was completed three years ago.
The
$8 billion plus for restoration of LIRR service on the old Rockaway
Queens branch has yet to advance beyond a final planning study released
in 2019.
The
$2.7 billion plus for the NYC Department of Economic Development
Brooklyn-Queens Waterfront Street Car Connector is undergoing an
environmental review. The project is counting on an FTA $1 billion or
more Full Funding Grant Agreement to be matched by local sources. The
MTA has not offered to sponsor a grant application, perform design and
engineering, construct, maintain or operate this new transportation
system. Neither NYC DOT or NYC EDC have any experience in managing
advancement of or actually running a street car system.
The study for the Utica Avenue Brooklyn NYC Transit subway extension was included in MTA 2015 - 2019 $32 billion Five Year Capital Plan finally began in 2020. Construction costs could be $5 billion.
There
is no current activity for the $800 million new NYC Transit #7 subway
station at 10th Avenue & 41st. This was deleted from original $2.4
billion Hudson Yard#7 subway extension to save $500 million.
The
Red Hook Brooklyn subway extension from NYC Transit #1 subway line
from the Rector Street downtown Manhattan station to Red Hook was
proposed four years ago as a planning suggestion. There is no current
activity to advance this project at a cost of $3.5 billion.
The
NYC Transit Staten Island North Shore Bus Rapid Transit $600 million
project is in the planning and environmental review process. There is
no funding programmed within the current $51 billion MTA 2020 - 2024
Five Year Capital Plan to support advancement of this project. Future
$590 million in funding may be required for final design and
engineering, land acquisition, business relocation, and actual
construction.
The
Staten Island West Shore Bus Rapid Transit planning study is under way.
Future funding of $1.485 billion may be required for preliminary and
final design and engineering, land acquisition, business relocation,
construction, purchase of vehicles along with a maintenance and storage
facility.
The
$1.1 billion Niagara Frontier Transportation Authority Light Rail
Extension to Amherst. The project is currently in the environmental
review stage.