From the Queens Courier:
The city’s extended closure of an overpass bridge in Flushing is set to end by 2016, according to a Department of Transportation (DOT) spokesman. But the long wait could continue to hurt local business owners.
LIRR train tracks cut through 149th Street, with an overpass bridge connecting the two sides of the street. The bridge has been closed since 2009, according to residents and business owners in the area.
According to a DOT spokesman, a new bridge was ready to open in 2012, but during a final inspection the department found cracks in the foundation, leading the department to keep the bridge closed.
The lack of a bridge in the area left several businesses on 41st Avenue disconnected from the other side. Traffic withered away as a result, business owners said, and led to a noticeable reduction in customers visiting the stores on 41st Avenue, near the 149th Street overpass bridge.
The city plans on completing a final design in 2014. And in the fall of 2015 the spokesman expects a construction contract to be hashed out. The new overpass bridge should be completed within six months after that.
1 comment:
Business has been bad since 2009? It has city wide. The fifteen second detour around the block isn't responsible.